Wycliffe Gardens

The project is made up of traditional properties consisting of 1,2 and 3 bedroom flats and maisonettes.

Internal works as required including new kitchens, bathrooms, rewires and heating systems.

This project commenced on the 12th September 2011, comprising full refurbishments to 82 properties.  The scheme is scheduled to finish  by April 2012.

Site Office
75 Wycliffe Gardens

Shipley  BD18 3NH
tel: 01274 254355

Site Manager: Richard Greenwood
Customer Relationship Officer: Julie Stead

 

Rosebery

The project is made up of traditional properties consisting of 1,2 and 3 bedroom flats, bedsits and maisonettes.

Internal works as required including new kitchens, bathrooms, rewires and heating systems.

This project commenced on the 18th August 2011, comprising full refurbishments to 122 properties and is scheduled for completion in June 2012.

Site Office
Booth Street
Off Church Street
Shipley  BD18 2NR
tel: 01274 254352

Site Manager: Marc Clarkson
Customer Relationship Officer: Nikki Airey

 

Girlington

Four Lane Ends project is made up of traditional properties consisting of 1,2 and 3 bedroom flats and 2 and 3 bedroom houses.

Internal works as required including new kitchens, bathrooms, rewires and heating systems.

The first property commenced on the 4th April 2011, and the scheme comprises full refurbishments to 99 properties. The scheduled completion date is December 2011.

Girlington is made up of traditional properties consisting of 1 and bedroom flats and 2 and 3 bedroom houses.

Internal works as required including new kitchens, bathrooms, rewires and heating systems.

Girlington commenced on the 26th September 2011, and the scheme comprises full refurbishment to 68 properties.  The scheduled completion date is March 2012.

Site Office
Manningham Labour Club (Land to rear)
Bull Royd Lane
Manningham BD8 0LJ
tel: 01274 254370

Site Manager: Andy Airey and Roland Baines
Customer Relationship Officer: Hellen Buss


Thornton

The project is made up of traditional properties consisting of 2 and 3 bedroom houses and 1 and 2 bedroom flats.

Internal works as required including new kitchens, bathrooms, rewires and heating systems.

This project commenced on the 4th April 2011, comprising full refurbishments to 165 properties.  The scheduled completion date is March 2012.

Site Office
47a Springhead Road
Thornton
Bradford BD13 3BU
tel: 01274 254388

Site Manager: Terry Stanton
Customer Relationship Officer: Rebecca Wilson